Construction of the Carlisle Dog Park is anticipated to start the week of August 12th and last for 12-15 weeks. The project will be closely coordinated with the Recreation Department and supervised by the Building Commissioner.
The first two weeks will primarily entail tree removal, which is expected to be the noisiest aspect of the job. After that, erosion controls will be installed in coordination with the Conservation Department and Trails Committee, with the rest of project to follow.
Typical work hours will be 7:00AM-4:00PM Monday – Friday, and some Saturdays from 9:00AM – 3:00PM.